Charged by the Contractor Hídépítő Ltd. Pont-TERV Ltd. has made
the independent statical control analysis for the superstructure of the H7 bridge
at the junction of the M7 and M70 Motorways on the Becsehely-Letenye section
The superstructure is a two-span extradosed P.C. beam bridge,
witha a total length of 114.24m. The spans are 61.98+52.56m long. The cross section
is a three-cell P.C. box girder.
For the statical modelling of the superstructure the TDV RM2000
program has been used.
|